The long-awaited Highway 25 bypass could be delayed for more
than a year as Council of Government members moved to avoid a legal
showdown with property owners along the proposed route.
Hollister – The long-awaited Highway 25 bypass could be delayed for more than a year as Council of Government members moved to avoid a legal showdown with property owners along the proposed route.

In an attempt to satisfy property owners, who thought COG was not offering a high enough price for their land, and avoid a costly and time-consuming legal battle, the COG Board chose to quash the eminent domain process begun earlier this year and seek new appraisals for 13 pieces of land needed for the bypass, according to COG Executive Director Tom Quigley.

“We don’t have any reason to have a belief that the appraisals were done wrong, but the land owners challenged it and said we low-balled it,” Quigley said. “We’re going to do a second appraisal and, based on that, review the offers. If we need to make adjustments, we will.”

The amount of money offered to landowners varied depending on what type of land it is and how it is zoned, said COG Traffic Planner Mary Dinkuhn.

“It would have been a lot of money to go through litigation,” Quigley said, adding, “We want a sense of fairness.”

Once the bypass project is complete, Caltrans will cede control of San Benito Street – currently part of Highway 25 – to Hollister. Business owners in downtown Hollister are eager to see the city make San Benito Street more pedestrian friendly and attractive to residents and shoppers. Some are discouraged, yet not surprised, with this latest set back to the long-planed bypass project.

“It just doesn’t surprise me … it’s a huge concern” said Jackie McAbee, owner of Just Friends, a downtown gift shop. “Unless something is done immediately, the town is going to look like a ghost town.”

COG did not have to cease the eminent domain process – through which governments take land from private owners, who are compensated, for public use – in order to get new appraisals on the land, according to Dinkuhn. But, she said, COG was advised by it’s private legal counsel to stop the process and get new appraisals, “Due to a large number of concerns with procedures and concerns with property owners … various procedural issues.” Dinkuhn said she was unable to elaborate on the concerns.

It will take about three months for COG to find a company to perform the new appraisals, which will then take about two and a half months to complete, Quigly said. Once the appraisals are done, COG will begin re-negotiating with the land owners. The entire process will delay the bypass project for about one year to 15 months, he said.

According to Dinkuhn, COG has acquired about 50 percent of the property needed for the bypass project, which is eventually supposed to create a new leg that circumvents Hollister’s downtown and connects with Airline Highway near Safeway.

The plan has been in the works since at least 1988, when voters passed Measure A, pushing up the sales tax by a half-cent to help pay for highway improvements. Since then, the $24 million project has gotten $12 million from Measure A, $7 million in traffic impact fees and $4 million each in developer fees and federal funds.

Luke Roney covers politics and agriculture for the Free Lance. Reach him at 831-637-5566 ext. 335 or at [email protected]

Previous articleQuestions on recall
Next articleSan Juan Council raises water rates
A staff member wrote, edited or posted this article, which may include information provided by one or more third parties.

LEAVE A REPLY

Please enter your comment!
Please enter your name here