If worst-case scenarios come true, reshuffling of highway
projects because of decreases in revenues from the slow economy
could mean years of delays.
GILROY – If worst-case scenarios come true, reshuffling of highway projects because of decreases in revenues from the slow economy could mean years of delays for portions of an interchange and widening project crucial to serve major regional shopping centers and a major business.

To officials in Gilroy, the funds that are supposed to go to the projects are as good as gone – meaning worries about potentially horrendous traffic snarls at the shopping centers and Gilroy Foods.

“The projects will not be funded,” Gilroy Mayor Tom Springer said. “The money has shifted up north and we won’t get our roadway segment.”

But Santa Clara County leaders and transportation officials said there was no reason to panic yet: with key information and decisions still yet to come, the sales-tax drops could mean only delays of a few months – or none at all.

“Nobody’s taken money away from anyone else,” said County Supervisor Don Gage. “We’re trying to make good on everything we said we’d do.”

At issue is at least $6 million in funding for several individual projects at the junction of U.S. 101 and state Highway 152 and along the 152 roadway itself as it heads east toward Pacheco Pass.

A signalization and widening project that’s already begun to serve the two shopping centers – especially the Pacheco Pass Center and its new Lowe’s and Costco stores where 101 and 152 meet – will not be effected, officials said. That project would allow drivers to turn into the shopping centers from 152.

But several other parts of the project have been cast into uncertainty, including a new interchange at U.S. 101 and Highway 152 and widening work eastward on Highway 152 that’s meant to allow traffic to move more smoothly through the area, and a new stoplight and turn area serving the Gilroy Foods plant east of the shopping centers.

Under a new priority system adopted by county supervisors last month, those projects are now lumped into a category of other roadway improvements that county analysts have projected could receive only partial funding from the declining Measure B sales tax monies.

Under the new priority system, funding construction of an $82 million interchange at U.S. 101 and state Highway 85 in Mountain View is the top priority and would be first in line for funds from the measure.

In the second tier of priorities would be another $60 million in various projects, ranging from congestion relief among expressways in the northern part of the county, traffic signal synchronization and bicycle paths.

The Highway 152 projects in question are lumped into a third tier of $52 million in projects where only partial funding is projected. That tier also includes work on Highway 17 and several items of Caltrain funding.

Another $1 million in intersection improvements at Highway 152 and Ferguson Road are currently even lower on the priority list, into a fifth-tier priority category where no projected funding exists.

According to Measure B program administrator Jeff Davis, engineering, design and environmental studies may continue on those projects. But the county has decided to wait until more updated sales tax projections come out early next year in order to figure out which of the projects can be afforded under measure funds and authorized for construction.

“The staff is very conservative,” Davis said. “The last thing we want to do is move ahead through a project and find out a year or two later we can’t finish something we started in construction.”

It’s premature to say how much money will be available then for the Tier Three projects until the county sees the numbers, Davis said.

“Unless we get a very bad revenue quarter in December, assuming revenues are on target, I would say a good portion of the Tier Three may be fundable,” he said. “But that means that supervisors will have to prioritize those projects.”

Springer said officials have been presented a more dire picture: there’s no money to fund construction.

“As far as we know, these are delayed indefinitely and not being done,” he said.

While officials will ensure the Newman and Regency centers continue, Springer said, it would mean either finding money somewhere else to pay for the rest of the highway projects – or else adopting a city measure that says benefits from east side development are too important to be slowed or effected by the traffic impacts.

And Gilroy Foods – which has been waiting for improvements out front of its plant for years – could become frustrated and close its facility, he added.

“The bottom line is we want the $6 million (back),” Springer said.

But Gage said there’s no reason to panic – the county didn’t move the $6 million out of Highway 152, it just hasn’t let the contracts go (out) yet until the numbers come back.

“Six million, in comparison to millions on Measure B – that’s a very small amount we can find …” he noted. “No one is shortchanging South County.”

Previous article27th Assembly candidates tout party line
Next articleHilario “Moe” Angulo
A staff member wrote, edited or posted this article, which may include information provided by one or more third parties.

LEAVE A REPLY

Please enter your comment!
Please enter your name here