The new northbound lanes of U.S. 101 are striped and ready to be opened just north of Morgan Hill.

When Gov. Gray Davis orders the opening of all eight lanes of
U.S. 101 from Metcalf Road to Cochrane Road Monday around noon, the
largely ceremonial phone call he’ll place from the ribbon-cutting
ceremony near the Coyote Creek off-ramp will symbolize more than
the unplugging of years of freeway congestion.
When Gov. Gray Davis orders the opening of all eight lanes of U.S. 101 from Metcalf Road to Cochrane Road Monday around noon, the largely ceremonial phone call he’ll place from the ribbon-cutting ceremony near the Coyote Creek off-ramp will symbolize more than the unplugging of years of freeway congestion.

For the residents, politicians and business leaders with a hand in the five-year $80 million project, the breaking of the highway’s bottleneck puts cement to a loose but solidifying notion that South Valley has become a political and economic force in the region and the state.

Since 1996, when Santa Clara County voters approved the tax measure (Measure B) that funded U.S. 101 and other freeway improvements, area leaders fought to widen the scope of the project from three lanes on each side to four, won a court case brought against Measure B backers and convinced the federal government to grant more time to acquire open space to mitigate for impacts to an endangered butterfly.

“Three lanes wouldn’t have accomplished anything, and the other issues were huge hurdles because they could have shut us down entirely,” said Santa Clara County Supervisor Don Gage.

The Valley Transportation Authority predicts commute times to decrease by 12 minutes. In terms of speed, northbound and southbound commuters will be able to travel at 65 mph. Previously, speeds hovered between 28 and 35 mph averages.

The U.S. 101 widening project was finished six months ahead of schedule. The VTA said the rearranging of the order of work was a large factor in speeding up the project. The change in scheduling added $2.1 million to the overall project, a tab the VTA justified.

“When you look at saving 12 minutes a day moving goods and products into and out of the area, the widening project saves you $20 million a year,” said VTA Spokesperson Anne-Catherine Vinickas. In theory, being ahead of schedule six months is a nearly $8 million boost to the area’s economy.

Vinickas said she traveled the southbound lanes around 7:30 p.m. Wednesday, just hours after those four lanes were opened.

“I’ve been slowed to a stop before even at that late hour, but yesterday it was clear driving at the predicted 65 mph,” Vinickas said.

Vinickas said traffic will run even smoother in July 2004, the expected completion date for the U.S. 101 and Highway 85 interchange project. The commuter lanes of those freeways will be directly connected when the project is done. Currently, when switching between the two freeways, car-pooling vehicles must cut across regular lanes to get back into the designated carpool lane of the other freeway.

“It means easier and faster access for all drivers because the mixed lanes will see no weaving from car-poolers,” Vinickas said. “It really helps everyone on the freeway.”

Gage, along with Gilroy Mayor Tom Springer and Morgan Hill Mayor Dennis Kennedy, served on the VTA during the planning stages of the Highway 101 project. Kennedy’s term has since expired.

Springer, who was in Sacramento for the governor’s May budget revise, could not be reached for comment Thursday. But when a section of the project opened in February, Springer called the highway a “quality of life issue.”

“We’re talking about adding 10 minutes to a person’s life and taking away a whole lot of frustration people feel when they’re stuck in a bottleneck,” Springer said then. “Right now, you have people asking themselves, ‘Why should I go down there to shop?'”

Bill Lindsteadt, the executive director of the Gilroy Economic Development Corporation, uses one word when he’s asked about his feelings on the highway widening.

“Terrific.”

Lindsteadt’s chief function at the EDC was to bring new business to the area, a task that only gets easier when getting into and out of it is less difficult.

“I don’t think Lowe’s and Costco and other major stores based their decision (to come to the area) on the highway widening,” Lindsteadt said. “It’s sort of a reach as far as their regional draw is concerned quite frankly, but we do know folks shopping at the Costco are coming from San Jose because of parking and traffic issues at the one up there.”

Lindsteadt has been working with Gavilan College and the Small Business Development Center for several months to bring the biotech industry to the area. Currently, a Canadian firm is trying to land the financial support to set up manufacturing of a new form of fire retardant here.

“Once you get companies noticing a difference in getting their product to market, there will be a ripple effect of other companies that want to come here,” Lindsteadt said.

Previous articleAnzar’s Monde wins MTAL long jump
Next articleA Baler sweeper
A staff member wrote, edited or posted this article, which may include information provided by one or more third parties.

LEAVE A REPLY

Please enter your comment!
Please enter your name here